Corporate & Commercial10 min read
Contractor not paid or project delayed in Qatar: what does the law say?

Faysel Al-MohannadiLawyer admitted before the Court of Cassation · Reviewed on
Short answer
Under Qatar's Civil Code, the employer pays the contractor when the work is delivered, unless the contract or custom says otherwise, and the contractor must finish on time. An unpaid subcontractor can claim directly from the employer, up to what it still owes the main contractor. Commercial disputes go to the Investment and Trade Court, or to arbitration if agreed.
What does Qatari law say when a contractor is not paid?
The employer must pay the contractor when it takes delivery of the work, unless the contract or custom says otherwise (Civil Code, Article 697). Articles 682 to 715 of the Civil Code (Law No. 22 of 2004) govern contracting («المقاولة»). Most apply only where the contract is silent, but some cannot be excluded, such as the ten-year liability (Article 715).
Construction contracting carried out as a business is a commercial act (Trade Law No. 27 of 2006, Articles 4 and 5), which affects the court, notices and limitation.
| Issue | What the law says | Article |
|---|---|---|
| When payment is due | On delivery, unless the contract or custom says otherwise | 697 |
| Work in parts or at unit rates | The contractor may be paid for each part completed, unless agreed otherwise; payment implies acceptance unless made on account | 698 |
| No agreed price | The value of the work when contracted, plus materials supplied | 699 |
| Changes to a lump-sum design | No extra pay, unless the employer caused the change, or authorised it and agreed the price | 709 |
| Estimate exceeded | The contractor must notify the increase promptly or lose it; if the excess is serious, the employer may withdraw, paying for work done | 708 |
| Rising costs of materials and labour | No change to the contract, save the judge's power in exceptional events | 700 and 171 |
| Employer refuses delivery | Treated as delivered if it refuses without good reason after a formal notice | 693 |
| Defects at delivery | Refusal only if the work is unfit for its purpose; otherwise a price cut or repair. For a building on the employer's land that would be very harmful to remove, only a price cut or repair, plus any compensation | 694 and 710 |
| Defects after delivery | Delivery ends liability for visible defects; hidden ones must be notified promptly | 696 |
| Subcontracting | Allowed unless the contract forbids it or the work depends on the contractor personally; the main contractor stays liable | 701 |
| Collapse or defects threatening stability | Contractor and engineer jointly liable for ten years from delivery | 711 |
What happens when a construction project is delayed?
The contractor must finish within the agreed time or, if none was agreed, a reasonable time (Civil Code, Article 687). If the delay makes on-time completion hopeless, the employer may ask for termination before the completion date (Article 689).
- Compensation. Late performance must be compensated unless due to an outside cause (Article 256), and as a rule only after formal notice, unless agreed otherwise (Article 260).
- Delay penalties. Compensation fixed in the contract is not due if the debtor proves there was no harm. The court may reduce it if grossly excessive or if the work was partly done, and contrary clauses are void (Articles 265 and 266).
- Delay caused by the employer. If the employer does not do its part in time, the contractor may set a reasonable deadline, then ask for termination with compensation (Article 692).
What payment security do contractors and subcontractors have?
An unpaid subcontractor can claim directly from the employer, up to what the employer owes the main contractor when the claim is filed (Civil Code, Article 702). Workers on the job have a similar right.
- Subcontractor's privilege. Subcontractors who attach sums held by the employer or the main contractor gain a privilege over them, ranking ahead of anyone to whom the main contractor assigned its claim (Article 702).
- Withholding performance. Where both sides' obligations are due, each may withhold performance while the other does not perform, unless agreed or custom says otherwise (Article 191).
- Right of retention (lien). A person bound to hand over a thing may keep it until the other side offers to perform a connected due obligation or gives adequate security. It gives no priority and ends once the thing leaves the holder's hands (Articles 280, 282 and 284).
- Contractors' privilege. Contractors and engineers who build, rebuild, restore or maintain buildings or other structures have a privilege over them, limited to the value their work added at sale. It must be registered (Articles 1185 and 1064).
- Bank guarantees. The bank pays on demand during the validity period and cannot refuse because of the underlying dispute (Trade Law, Articles 406, 409 and 411).
Freezing assets before judgment changed with the 2024 Judicial Enforcement Law; see our guide to recovering a debt in Qatar.
What time limits apply, including the ten-year liability?
A claim for unpaid construction work is time-barred after 15 years as a general rule, or 10 years between traders, counted from the due date (Civil Code, Articles 403 and 410; Trade Law, Article 87).
| Claim | Time limit | Source |
|---|---|---|
| Contract price, general rule | 15 years from the due date | Civil Code, Articles 403 and 410 |
| Obligations between traders about their business | 10 years from the due date, unless the law sets less | Trade Law, Article 87 |
| Fees of engineers and other professionals | 5 years from completing the work, or 15 years if a written instrument records the debt | Civil Code, Articles 405 and 408 |
| Ten-year liability for collapse or defects threatening stability | 10 years from delivery, or less if the building was meant to last less | Civil Code, Article 711 |
| Claim under the ten-year liability | 3 years from the collapse or the discovery of the defect | Civil Code, Article 714 |
The ten-year liability («الضمان العشري») applies even if the defect comes from the ground or the employer approved the work (Article 711). The engineer answers for design defects, and for execution defects if supervising; the contractor answers for design defects only if they were obvious or the designer works for it (Articles 712 and 713). Clauses excluding or limiting this liability are void (Article 715).
Limitation is interrupted by a court claim, an attachment or the debtor's acknowledgment, among other acts (Articles 413 and 414), and the parties cannot agree on a different period (Article 418). Contract clauses requiring notice of claims within a set time are a separate matter, so read them early.
Which notices and records should you keep?
Several contracting rights in the Civil Code depend on a notice given in time, so send notices in writing and keep proof of delivery.
- An estimate will be exceeded: notify the employer promptly (Article 708).
- The employer's materials are defective, or something holds up the work: notify at once (Article 686).
- A lump-sum design changes: get the employer's authorisation and agree the price (Article 709).
- The work is complete: notify the employer, and send a formal notice if it will not take delivery (Article 693).
- You claim compensation: give formal notice first (Articles 260 and 261); in commercial matters, by registered letter with acknowledgement of receipt (Trade Law, Article 81).
Keep the signed contract and drawings, approved variations, payment applications and certificates, invoices, site diaries, meeting minutes, correspondence, photographs and handover records. Foreign-language documents need an Arabic translation at the Investment and Trade Court (Law No. 21 of 2021, Articles 17 and 19).
If site evidence may be lost, for example before work is covered up, the urgent matters judge can be asked to inspect it, with an expert if needed (Civil and Commercial Procedure Law, Articles 331 and 332).
Which route fits: settlement, arbitration or the Investment and Trade Court?
A construction payment dispute in Qatar is resolved by settlement, by arbitration under a written arbitration agreement, or in court, where the Investment and Trade Court hears commercial disputes.
| Route | When it fits | What to know |
|---|---|---|
| Negotiation or mediation | Any stage | The mediation law (Law No. 20 of 2021) applies to disputes within the Investment and Trade Court's jurisdiction (Law No. 21 of 2021, issuing Article 3) |
| Arbitration | A written arbitration agreement exists | A court rules a claim inadmissible if the other side raises the agreement before defending on the merits (Arbitration Law No. 2 of 2017, Articles 7 and 8). Administrative contracts need the Prime Minister's or his delegate's approval (Article 2) |
| Investment and Trade Court | Commercial contracts, disputes between traders about their business, public-private partnerships | Excludes matters for the administrative circuits. Filing is online, and parties may file an expert report (Law No. 21 of 2021, Articles 7, 14 and 26) |
| Payment order | A money debt proved in writing, fixed and due | Issued by a single judge, whatever the amount, with no prior notice to pay (Law No. 21 of 2021, Article 8; Civil and Commercial Procedure Law, Article 147) |
Where the arbitral tribunal cannot act in time, the competent judge may order interim measures without the request waiving arbitration (Arbitration Law, Article 9). Judgments and awards are enforced through the Enforcement Court: see arbitration in Qatar, enforcing a judgment in Qatar and reviewing a contract before you sign.
When should you speak to a lawyer?
These are signs it is worth asking early:
- The employer disputes quantities, variations or quality, or is deducting delay penalties.
- You exceeded an estimate, or did extra work without a signed variation.
- You are a subcontractor and the main contractor has stopped paying.
- A bank guarantee has been called, or is about to expire.
- The contract has an arbitration clause, or the employer is a government body.
- A building defect has appeared, and the ten-year or three-year limits may be running.
What the law says
This guide relies on Articles 682 to 715 of the Civil Code (Law No. 22 of 2004) on contracting, and on its Articles 171, 191, 256 to 266, 280 to 284, 403 to 418, 1064 and 1185. It also relies on Articles 4, 5, 81, 87, 406, 409 and 411 of the Trade Law (Law No. 27 of 2006), issuing Article 3 and Articles 7, 8, 14, 17, 19 and 26 of the law establishing the Investment and Trade Court (Law No. 21 of 2021), and Articles 2, 7, 8 and 9 of the Arbitration Law in Civil and Commercial Matters (Law No. 2 of 2017). Finally, it relies on Articles 3 and 6 of the Judicial Enforcement Law (Law No. 4 of 2024) and Articles 147, 331 and 332 of the Civil and Commercial Procedure Law (Law No. 13 of 1990), as shown on Al Meezan on 21 October 2026.
Read on Al MeezanQuestions people ask
Yes. Article 702 of the Civil Code lets a subcontractor claim directly from the employer, up to what the employer owes the main contractor when the claim is filed. Its rights rank ahead of anyone to whom the main contractor assigned its claim against the employer.
Not as a general rule. Rising prices of materials and labour do not change the contract (Article 700), unless exceptional, unforeseeable general events make performance so onerous that a judge reduces the obligation to a reasonable level (Article 171).
Ten years from delivery for collapse or defects threatening a building's stability and safety, or less if the building was meant to last less (Article 711). A claim must be brought within three years of the collapse or the discovery of the defect (Article 714).
Yes, at any time before completion, but it must compensate the contractor for expenses, work done and the profit it would have made. The court may reduce the lost-profit part where the circumstances make that fair (Article 707).
Guides on this
All guides
Corporate & CommercialHow to recover money someone owes you in QatarMost creditors in Qatar start with a written demand. If the debt is a sum of money, in writing, fixed in amount and due, a payment order can replace a full lawsuit. A disputed debt needs a civil claim. Judgments, court orders, returned cheques and notarised settlements go straight to the Enforcement Court under the 2024 Judicial Enforcement Law.9 min read
Corporate & CommercialHow does arbitration work in Qatar, and when does it apply?Arbitration in Qatar needs a written agreement, either a contract clause or a separate agreement, and is governed by Law No. 2 of 2017. Matters that cannot be settled by compromise cannot be arbitrated. Cases run under an institution's rules, such as QICCA's, or without one, and end in an award open only to annulment within one month.9 min read
Corporate & CommercialBefore you sign a contract in Qatar: the clauses to checkBefore signing a contract in Qatar, check who the other party is and who may sign for it, the scope, payment and security, any penalty clause, termination rights, the governing law and forum or arbitration, the prevailing language, and whether notarisation or registration is required. Civil Code Law No. 22 of 2004 lets a judge reduce an excessive penalty.8 min read
Corporate & CommercialYou won the case in Qatar: how do you collect what the court awarded?A judgment is not paid automatically. Once it is final or provisionally enforceable, the winner files an enforcement request with the Enforcement Court, and the debtor gets ten working days to pay. If they do not, the judge can attach and sell their accounts, salary, property and vehicles, and take other graduated measures under the 2024 Judicial Enforcement Law.9 min read
Corporate & CommercialHow does Qatar's Commercial Agents Law work for a foreign brand and its Qatari agent?Under Law No. 8 of 2002, only a Qatari national or a wholly Qatari-owned company registered with the Ministry of Commerce and Industry may act as a commercial agent. Sole distributors count as agents; unregistered agencies are not recognised. Termination or non-renewal can entitle the agent to compensation. Unless agreed otherwise, the Investment and Trade Court hears disputes.10 min read
Corporate & CommercialSettlement, mediation, arbitration or court: how do they compare in Qatar?Qatar offers four routes for a civil or commercial dispute: settlement, mediation (Law No. 20 of 2021), arbitration (Law No. 2 of 2017) or court, the only one needing no agreement between the parties. Mediators cannot impose a solution; arbitrators and judges decide. Judgments, awards and court-certified or notarised settlements are enforceable under Judicial Enforcement Law No. 4 of 2024.11 min read
Unpaid for construction work, or facing delay penalties?
Gather the contract, the latest payment records and the correspondence, and ask about your situation.